- Log the day the owner gets the notice, and count ten days from that date.
- Correct inaccurate information within the window, but only if the notice contains errors.
- Send a bond copy, with the surety and bonding agent's name and address, only if a payment bond was recorded under section 33-1003.
An Arizona owner who gets a 20-day preliminary notice may owe two ten-day responses: fix inaccurate information and send any recorded bond copy. If you own an Arizona job, or handle the mail for one, a preliminary notice can arrive with little warning. This post covers the two owner duties that carry a ten-day clock. It is general information in plain words, not legal advice. The governing text is Arizona Revised Statutes section 33-992.01, which sets out what a "preliminary twenty day notice" must contain and what the owner must do after receiving one.
Key takeaways
What the notice tells you
The notice states its own character. The form includes this line: "In accordance with Arizona Revised Statutes section 33-992.01, this is not a lien and this is not a reflection on the integrity of any contractor or subcontractor." That line describes the notice itself and does not end the owner's ten-day duties under section 33-992.01. The notice says it is not a lien, and it says it is not a judgment on anyone's integrity.
The form also includes bracketed text saying that acknowledgment language from section 33-992.02 belongs at that spot. If the copy you received still shows that bracketed text instead of the acknowledgment language, look at it again before you file it. The statute that text points to is section 33-992.02, and this post does not cover it.
The form also explains what a bond answer should look like: "If any payment bond has been recorded pursuant to section 33-1003, a copy of the bond and the name and address of the surety company and bonding agent, if any, providing the payment bond." That sentence tells you what information to expect if a bond exists on the project.
Reading the notice in full before you act is the simplest habit an owner can build. The notice is a short document, but it packs several separate pieces of information into a few lines. The statement that it is not a lien is one piece. The reference to the statute is another. The bond language is a third. Each piece can affect what your office needs to do next, so none of them should be skimmed past.
It also helps to separate the notice from any other paperwork that arrives on the same project. A preliminary notice is not the same thing as a demand for payment, a contract change order, or a court filing. Keep it in its own file, labeled with the project name and the date your office received it. That separation makes the ten-day tasks easier to find later.
Duty one and duty two both run ten days
Both owner duties are counted from the day the owner gets the notice, so the date your office logs the notice matters as much as anything else in the file.
The day the owner gets the notice is the anchor for both clocks. For that reason, a stamped or dated record of arrival is worth keeping. Record the date the owner actually got the notice. A later date logged by a desk does not replace it.
Duty one: correct inaccurate information. Within ten days after the owner gets the notice, the owner or other interested party must furnish all information necessary to correct any inaccuracies in the notice, under section 33-992.01, subsection J, or lose as a defense any inaccuracy of that information.
In practice, this means comparing the notice against your own records. Check the project details, the names of the parties, and the contract information the notice relies on. If something is wrong, send the correct information within the ten-day window. The cited subsection J is part of the same statute and is worth reading alongside this duty.
Duty two: send a copy of any recorded bond. Within ten days after the owner gets the notice, if any payment bond has been recorded under section 33-1003, the owner must provide a copy of the payment bond, including the name and address of the surety company and bonding agent, to the person who gave the notice.
This duty has a condition. It applies only if a payment bond has been recorded under section 33-1003. If no bond was recorded, no bond copy is required.
Compare the two duties side by side
| Item | Duty one: correct information | Duty two: send bond copy |
|---|---|---|
| Trigger | The notice contains inaccuracies | A payment bond has been recorded under section 33-1003 |
| Deadline | Within ten days after the owner gets the notice | Within ten days after the owner gets the notice |
| What to send | All information needed to correct the inaccuracies | A copy of the bond, plus the name and address of the surety company and bonding agent |
The table shows the main difference. Duty one depends on whether the notice is wrong. Duty two depends on whether a bond was recorded.
The two duties can both apply to the same notice. A notice can contain an inaccurate project detail and sit on a project that also has a recorded bond. When that happens, your office has two separate tasks inside the same ten-day window. Handling them in one pass, with one checklist, is often the most reliable approach, but each task still needs its own proof that it was done.
Illustrative example: one notice, two checks
An office logs a notice on day 0. It finds that the project's street name is wrong, so it sends the correct name within ten days. Its search finds no recorded bond, so duty two does not apply, and the office keeps a dated note of the search. A second project logged the same way has a recorded bond, so the office sends the bond copy, with the surety's and bonding agent's name and address, inside the same window.
How to check the notice for inaccuracies
Duty one asks you to find errors, so the review step needs a method. Start with the parts of the notice that name people and places. Confirm that the project name, address, and parties match your contract and your recorded documents. Then move to the description of the work and any amounts or dates the notice states. Check each field the notice states, not just the most obvious ones.
Use your own source documents as the standard. The quoted duty asks for "all information necessary to correct any inaccuracies," which points you toward providing the correct facts, not just saying that something is wrong. For each error you find, write down what the notice says, what the correct information is, and which document in your file shows the correct version. A short table or list works well for this. Keep it with the copy of the notice.
Do not guess. If a detail is unclear, pull the underlying record rather than filling the gap from memory. An owner who sends a correction based on an assumption can create a new inaccuracy, and the statute places the burden on the owner to furnish the information that corrects the notice. Accuracy matters more than speed within the window, but the window still matters.
When the review turns up nothing wrong, record that conclusion too. A dated note saying the notice was checked and no inaccuracy was found is useful if the question comes up later. It shows the office reviewed the notice inside the statutory period rather than ignoring it.
How to handle a recorded payment bond
Duty two depends on a fact that owners sometimes do not know: whether a payment bond was recorded under section 33-1003 for the project. Your office should check the public record for the project before the deadline arrives. If your files already include a recorded bond, the job is easier. If they do not, a search of the recording records for the project is the way to confirm what exists.
If a bond was recorded, the statute tells you what to send. The response includes a copy of the bond. It also includes the name and address of the surety company and the bonding agent who provided the bond. Pull the complete copy rather than a summary, and confirm that the copy matches the recorded version. Check the surety and agent details against the bond itself so that the names and addresses in your cover letter are accurate.
If no bond was recorded, you do not have to send one. Keep a note of how you determined that, including the date of the search and the place you searched. That note answers the question if a contractor later asks why no bond copy was sent. It also helps your office avoid sending a bond that does not exist, which would create confusion about the project's status.
The bond language on the notice form matches the statute closely. The form describes what a bond response includes if a bond was recorded. When the two versions seem to differ in wording, follow the statute, and ask an attorney if the difference affects your response.
Common mistakes to avoid
The most common mistake is treating the notice as a general request to be ignored. A preliminary notice that arrives and sits in a pile can run past the ten-day mark before anyone reads it. Assigning the notice to a named person on the day it arrives prevents that problem.
A second mistake is counting from the wrong date. Owners sometimes count from the date printed on the notice, the date a contractor says it was sent, or the date an email arrived in a shared inbox that nobody watches. The quoted duties count ten days from the day the notice is received. Choose one date, write it down, and use it for every calculation.
A third mistake is sending a correction that leaves out part of the required information. Duty one asks for all information needed to correct the inaccuracies. A partial reply that fixes one error but ignores another can leave the rest uncorrected. Review the full notice against your file before you send anything.
A fourth mistake is assuming the bond duty applies to every project. It applies only when a payment bond has been recorded under the cited section. An office that sends bond copies by habit, without checking the record, may send documents that were never required and may miss the real question of whether a bond exists.
A fifth mistake is failing to keep proof. A dated copy of what was sent and how it was delivered is the simplest protection an owner can have. Without it, the office has only memory to rely on.
Practical steps for the office
- Log the date the notice is received on the day it arrives. Both ten-day periods start from that date.
- Mark the ten-day deadline on the calendar from the logged date, and assign one person to own it. For related tracking, see job file closeout.
- Check the notice line by line against your project file. Note any inaccuracy in writing, with the source document that shows the correct information.
- Check whether a payment bond was recorded under section 33-1003 for this project. If one was, pull the bond copy and write down the surety company's and bonding agent's name and address.
- Send what is required and keep proof. Keep a copy of what was sent, the date it went out, and how it was delivered.
- Bring in a lawyer when the facts are unclear. A notice that involves a disputed bond or a disputed amount is a question for counsel.
Each of these steps is small, but together they form a complete response. An office that completes them in order, with a named owner for each, is much less likely to miss a deadline or send an incomplete reply.
Working with the contractor and your own counsel
The notice comes from a person who believes they supplied work or materials on your project. Keeping communication professional and written makes the process easier for everyone. A short cover letter that identifies the project, the notice, and the enclosed information is usually enough for a routine response.
Keep the cover letter factual. State what you are sending and why. Avoid adding opinions about the contractor's work, the amount owed, or the merits of any claim. The statute asks for information, and a response that sticks to information is easier to defend than one that argues.
Your own attorney can review the notice and your planned response before you send it. This is especially useful when the notice raises a disputed amount, names a party you do not recognize, or refers to a bond that you cannot find in the record. An attorney can also tell you whether any other deadline applies to the job, since this post covers only the two ten-day duties quoted above.
If your project has a general contractor, ask whether that party has already responded to the notice or plans to. Owners and contractors sometimes assume the other side is handling a notice, but the owner's duties under the statute apply regardless of what the contractor does. The first duty also covers other interested parties. Coordinate early so that the owner's response is not missed.
What this post does not cover
This post covers only the two ten-day owner duties quoted from section 33-992.01. It does not explain the acknowledgment language in section 33-992.02, the lien process, the bond itself, or any other deadline that may apply to a particular job. For those, read the statutes directly, ask an attorney who handles Arizona construction matters, or see lien suit deadlines.
Next step today: Find the date your office got the notice, write it on the calendar as the start of both ten-day windows, and check the project file for a recorded bond.
Related guides: Florida lienor payments: the 10-day owner notice · Florida bid-date change notice: 3 fields to include · California outdoor heat rules: 3 duties for crews.
Frequently asked questions
What if I cannot find a recorded bond?
Start by searching the recording records for the project and keeping a dated note of the search. If the result stays unclear, ask an attorney before you respond.
Does the response need a cover letter?
Yes, a short cover letter is usually enough for a routine response. It should identify the project, the notice, and any enclosed information.