- Furnish two items: a copy of the contract, and a statement of the amount due or to become due, if fixed or ascertainable.
- The statement must be signed under oath, and the signer should read it before signing.
- The 30-day clock runs from the demand, so record that date first.
- A missed or refused deadline, or a false or fraudulent statement, costs lien rights, bond rights, and attorney-fee rights.
You have 30 days from the written demand to furnish a copy of the contract and a sworn statement of the amount due under Section 713.16 of the Florida Statutes.
Key Takeaways
What the statute requires you to furnish
Under Section 713.16(1) of the Florida Statutes, a copy of the contract and a statement of the amount due or to become due, if fixed or ascertainable, must be furnished by any party to the contract upon written demand. The demand has to come from an owner or a lienor who contracts with or is employed by the other party to that contract.
| Item | What must be furnished | Source |
|---|---|---|
| Contract copy | A copy of the contract of a lienor or owner | 713.16 |
| Statement | A statement of the amount due or to become due | 713.16 |
| Amount limit | If fixed or ascertainable thereon | 713.16 |
| Furnished by | Any party to the contract | 713.16 |
| Upon demand of | An owner or a lienor contracting with or employed by the other party | 713.16 |
That sentence names two items. The first is a copy of the contract. The second is a statement of the amount due or to become due, and the statute limits that second item to amounts that are "fixed or ascertainable." This post does not explain how those words apply to any particular account, so take that question to your counsel.
The statement has requirements of its own. The statute refers to "the statement under oath," and it separately addresses "a false or fraudulent statement." Under this statute, the statement is a sworn document, so the person who signs it needs to know what it says before signing.
Whether a demand you received falls under this section depends on facts this post does not cover, including who made the demand and how that person relates to your contract. The section sits in Chapter 713 of the Florida Statutes, and every quote used in this post comes from that same section.
For an office, the practical question is often less about the statute's wording than about where the records are. A contract copy may sit in a project folder, an accounting system, or a paper binder. The figures for amounts due may come from a billing system built for invoicing rather than for a sworn statement. Those are facts your office can check internally before a deadline gets close, and checking them early is one of the most useful things a team can do.
How long you have: 30 days after the demand
The 30-day period in the quoted text runs from the demand. The statute says that a "failure or refusal to furnish the statement under oath within 30 days after the demand" deprives the person of his or her lien. The same section says an owner who does not provide the statement "within 30 days after demand" is not a prevailing party for attorney fees under a section this post does not quote.
The quoted text ties the 30 days to the statement. This post does not state a separate period for the contract copy, and it does not describe one.
A demand can reach an office in more than one form, and the quoted text does not say how the start date is fixed when the paperwork shows different dates. The safest habit is to write down the date of the demand itself, note separately the date and how it reached your office, and bring any conflict to counsel right away. The quoted text also contains no provision for extending the period, so this post will not guess at one.
Counting is simple, but errors happen. A calendar entry that only says "statement due" tends to get lost, so include the demand's date and the name of the person responsible for the response.
Because the deadline runs from the demand, a date recorded late can throw the whole calendar off. If the date printed on the demand differs from the date staff logged when it arrived, resolve the difference in the file and do not assume which one is right. Write down the reason for whichever date you choose, so the record shows how the deadline was set.
What a missed deadline or false statement costs
A failure or refusal to furnish the sworn statement within 30 days, or the furnishing of a false or fraudulent statement, costs the person who does it the rights listed below. The two triggers, a missed or refused deadline and a false or fraudulent statement, recur across the table, while individual rows name one or the other. Every row comes from the same section of the statute.
| Trigger | Consequence | Source |
|---|---|---|
| Failure or refusal to furnish statement under oath within 30 days after the demand | Deprives the person of his or her lien | 713.16 |
| Furnishing a false or fraudulent statement | Deprives the person of his or her lien | 713.16 |
| Failure or refusal within 30 days, or false statement | Deprives the person of his or her rights under the bond | 713.16 |
| Owner who does not provide the statement within 30 days after demand, or provides a false statement | Not a prevailing party for purposes of an award of attorney fees | 713.16 |
| Failure to furnish the requested statement within 30 days | Loss of the right to recover attorney fees in any action to enforce the claim of lien of the person requesting this statement | 713.16 |
| Item | What the quoted text says | Source |
|---|---|---|
| Deadline | Statement must be furnished within 30 days after the demand | 713.16 |
| Form | Statement must be furnished under oath | 713.16 |
| Missed deadline or refusal | Deprives the person of his or her lien | 713.16 |
| False or fraudulent statement | Deprives the person of his or her lien | 713.16 |
| Bond | Missed deadline or false statement deprives the person of rights under the bond | 713.16 |
| Owner's attorney fees | An owner who does not provide the statement within 30 days, or who provides a false or fraudulent one, is not a prevailing party for attorney fees | 713.16 |
| Attorney fees in a lien action (warning text) | Loss of the right to recover attorney fees in any action to enforce the claim of lien of the person requesting the statement | 713.16 |
The lien row is the consequence the quoted text names first. The bond and attorney-fee rows describe other rights the statute ties to the same missed or false statement. Read each row as a separate consequence, not as a list of steps that happen in order.
The table lists the consequences in the order the quoted text presents them. That order does not rank how often each one comes up, and it does not tell you which one matters most for a given dispute. Those questions depend on facts this post does not cover.
Timeliness and accuracy are both tested.
What the statute's warning says
The statute's warning says that failing to furnish the requested statement, signed under oath, within 30 days, or furnishing a false statement, "will result in the loss of your lien." The warning appears in capital letters in the statute's text, and it is the statute's own wording. This post does not claim that any particular demand includes it.
| Warning | Deadline named | Result stated | Source |
|---|---|---|---|
| Statement signed under oath | Within 30 days | Loss of your lien | 713.16 |
| False statement | Furnishing of a false statement | Loss of your lien | 713.16 |
| Statement not furnished | Within 30 days | Loss of right to recover attorney fees in any action to enforce the claim of lien | 713.16 |
| False statement | Furnishing of a false statement | Loss of right to recover attorney fees in any action to enforce the claim of lien | 713.16 |
The same provision contains a second warning about fees. It says that failing to furnish the requested statement within 30 days, or furnishing a false statement, "will result in the loss of your right to recover attorney fees in any action to enforce the claim of lien of the person requesting this statement."
Read the two warnings side by side. The first is about the lien. The second is about attorney fees in a lien action brought by the person who asked for the statement. Both start with the same 30-day deadline, and both are triggered by a false statement as well as a late one.
The warning language is useful for an office because it shows what the statute treats as serious. It uses the same terms for a false or fraudulent statement as it does for a missed deadline, so any response should be reviewed as carefully as the timing.
The warning is written for the person who receives the demand, which is why it spells out both the 30-day deadline and the two results together. A reader who skims past it may miss that a false statement carries the same lien consequence as silence. Read the full text of any demand you receive, including any warning printed on it, and compare it with the statute text linked above.
Steps to take before day 30
Record the date of the demand, count 30 days from it, and confirm that count with counsel. The quoted text runs its deadline from the demand, so the demand date is the reference point to write down first. Keep the date you received it as a separate entry. Once the demand date is on paper, these general practice steps can help you meet the rules quoted above:
- Name one person to own the response. Someone should be responsible for the deadline, the paperwork, and the sending of the response.
- Gather the contract and the account records. The statement covers the amount due or to become due, if fixed or ascertainable, so the signer needs the records that bear on that amount.
- Confirm who signs under oath. The quoted text requires the statement under oath, so the signer should be identified early, with time to read the statement.
- Compare the figures with the records before signing. A false or fraudulent statement leads to the same lien loss named for a missed deadline in the quoted text, so each figure should match a source document.
- Do not sign what the signer cannot confirm. If a number cannot be tied to a record, raise it with counsel before the statement goes out.
- Keep proof of the response. Record when and how the statement was sent, so the file shows what was furnished and when.
These steps are general office practice, not rules from the statute. The statute's rules are the ones quoted above, and anything beyond them should be checked with counsel.
Building a file that supports the response
A demand response is easier to defend when the file behind it is complete and orderly. Start with the demand itself, the date it was received, and any cover correspondence. Add the contract copy that was furnished, the records used to prepare the statement, and a note of who reviewed each figure.
Keep a short log of communications about the demand. Record each call, email, or meeting, the date, the people involved, and what was agreed. If the office later needs to show what it did and when, a clear log saves time and reduces the chance of a dispute over what was said. For the dispatch side of that file, see our related guide on job file closeout steps.
Decide early who keeps the original signed statement and where copies are stored. Two people should know where the file is, so that a single absence does not stall a response. The file should also show whether any figure changed between drafts, along with the reason for the change.
Keep the copy of the contract that was furnished identical to the version kept in your own files. If the two differ, a later dispute may turn on which one is the original, so note any difference and its cause in the file.
Finally, separate facts from assumptions in the file. If a number is an estimate, label it as an estimate and note the source. The quoted text requires the statement to be accurate, and a file that makes it easy to trace each figure back to its record supports that requirement. Our related guide lists Florida lien time limits to log on each job.
Worked example: one demand, one file
A demand carries a date of the 1st of the month. The office records the 1st as the demand date and the 5th as the date it arrived, then counts 30 days from the 1st. One person is named to own the response. The contract copy, the billing records for the amount due, and a note of who reviewed each figure are placed in one file. Any figure the signer cannot tie to a record is raised with counsel before the statement is signed. The file records the date and how the statement was sent. This example uses illustrative dates only.
If you cannot meet the 30 days
The quoted text does not describe an extension, so contact counsel before day 30 rather than planning around one. The statute treats a failure or refusal to furnish the statement under oath within 30 days as the point where the lien is lost, so waiting until the last day to ask a question leaves little room.
The quoted text also does not describe partial statements. If your records only support part of an answer, ask counsel what the statute means for a partial response before anything is sent. Do not assume that a partial response satisfies the statute, and do not fill gaps with estimates that have not been labeled as estimates. The quoted text does not describe a softer consequence for a partial or slightly inaccurate statement.
Some offices assume a demand can be answered with a general cover letter. The quoted text describes a statement under oath, which is a different kind of document from a letter. A letter sent on time does not, by itself, match that description, so confirm with counsel what must accompany any response.
If the office is unsure whether the demand is one the section covers, raise that question with counsel promptly as well. The answer may depend on facts about who made the demand and how that person relates to the contract, and those facts can take time to confirm.
Keep the demand, the contract copy, and any correspondence in one file. A complete file helps counsel answer the questions this post cannot.
Related guides: Florida notice of termination: 30 days after recording · Florida bid-date change notice: 3 fields to include · California needlestick log: 7 calendar days to record.
Questions readers ask about the 30-day demand
How many days do I have to answer a Florida written statement demand?
You have 30 days after the demand to furnish the statement under oath.
What two items does the demand require?
A copy of the contract, and a statement of the amount due or to become due, if fixed or ascertainable.
What happens if I miss the deadline or my statement is false?
The quoted text says the failure costs you your lien, your rights under the bond, and your right to recover attorney fees in a lien action.
Must the statement be signed under oath?
Yes, the quoted text repeatedly refers to the statement under oath, so the signer should read it before signing.
Does the statute allow an extension?
The quoted text describes no extension, so contact counsel before day 30 if you cannot meet the deadline.
This post is not legal or tax advice.