- Make the heat check its own line item on the board, with its own placement time and earliest reading time.
- Subtract the 20-minute settle once when both instruments are placed together, or from the later placement time when they are placed one after another.
- Check the wet-bulb wick length and water level at placement, and write that check on the log.
- Do not move the instruments during the wait. A new work area needs a new placement and its own wait.
- Report a late reading early instead of filling the gap with an old or guessed value.
Black globe and natural wet-bulb thermometers each need at least 20 minutes to settle before their readings can be used for a heat screen.
Key takeaways
Why the wait matters for dispatch
A crew that leaves the yard early and starts work a short time later has no heat reading in hand unless someone set up an instrument before they left. Most dispatch boards show a start time, a site address and a crew name. Very few show whether a heat check was taken, when it was taken, or whether it was taken at the place the crew is actually working. That gap is the reason for this post.
The instruments used in a heat screen do not give a useful number the moment they are placed. They have to sit in the air long enough to settle. The Canadian Centre for Occupational Health and Safety (CCOHS) says the black globe thermometer normally requires at least 20 minutes to come to equilibrium, and that the natural wet-bulb thermometer also requires at least 20 minutes to reach equilibrium.
That gives a team lead two waits to plan around, one for each instrument. If both are placed at the same moment, the two waits run side by side, and the delay stays close to one 20-minute wait. If they are placed one after another, the delay can run to a second full wait. Dispatchers rarely see that difference on the board, because the board only shows the crew start time. The simplest fix is to make the heat check its own line item with its own time, so it sits in the plan next to travel, permits and the morning briefing.
A reading taken before the instruments settle is not one you can rely on. So the useful question for a dispatcher is not "is there a thermometer on the truck?" It is "when does the reading become valid, and who is going to take it at that time?" Those two answers decide whether the screen happens before the crew starts or after they are already on the job.
What the heat screen is for
It helps to be clear about what the screen is for before deciding how much time to spend on it. The CCOHS page points to the ACGIH publication "2026 TLVs and BEIs" (or the most current booklet) as a source of recommended screening criteria for heat stress exposure for workers (Table 1). It also says that Table 1 is intended as a screening tool to evaluate if a heat stress situation may exist. For the heat-stress figures a team should set before outdoor work, see heat-stress figures to set before outdoor tech work.
The word that matters there is screening. A screen tells the team lead whether heat stress could be a concern at the site. It does not give a complete picture of one worker, one task or one body. It is a fast first check that tells you when to look closer. Dispatchers should not describe a passed screen to a crew as a guarantee, and should not describe a flagged one as a final finding. Both are an input to a decision made by the person in charge on site.
The same CCOHS text says the screening table assumes 8-hour workdays in a 5-day workweek with conventional breaks. That assumption is easy to miss. If your crews work longer shifts, rotate in shorter blocks, or work several weekends in a row, the table's stated assumptions may not match the job. Before anyone relies on the table for an unusual schedule, the team lead should check how well those assumptions fit the work.
Check the year too. The CCOHS page refers to the 2026 booklet, so the reference a team uses should be the newest version rather than whatever copy someone printed earlier. A dispatcher can help by asking the team lead which version the site procedure names, and by keeping a dated copy of that reference wherever screening is done.
Two instruments, two waits
The black globe thermometer and the natural wet-bulb thermometer measure different things, and each contributes a piece of the picture a screen needs. A globe reading responds to the heat around the instrument, including heat that comes from sunlight and warm surfaces, not only the air temperature. A natural wet-bulb reading responds to how easily moisture leaves a wetted wick, which depends on the humidity and the air movement around it.
Both instruments need settling time, and the CCOHS page gives the same minimum for each. The comparison below uses only the figures and conditions the source states.
Use the instrument names the source uses: the black globe thermometer and the natural wet-bulb thermometer. Mixing names across radio calls, job sheets and kit labels is an easy way to bring the wrong instrument to a job, and a wrong instrument means a wait that produces nothing useful.
| Item | What the CCOHS page states |
|---|---|
| Black globe thermometer | Normally requires at least 20 minutes to come to equilibrium reading |
| Natural wet-bulb thermometer | Also requires at least 20 minutes to reach equilibrium |
| Wick length (wet-bulb) | Extends 30 to 35 mm above the thermometer bulb |
| Exposed moistened wick (wet-bulb) | About 25 mm between the water and the bulb |
| Screening table assumption | 8-hour workdays in a 5-day workweek with conventional breaks |
Read down the first two rows and the scheduling problem is plain: the two waits are the same length, so the only question is whether they run together. The wick rows matter for the set-up, which is where the details live that decide whether the wet-bulb reading is usable at all. The last row is the one that decides whether the table fits your crews at all.
Setting up the wet-bulb wick
The natural wet-bulb reading depends on the wick being set correctly. The CCOHS page describes the set-up in measurable terms: the wick extends 30 to 35 millimetres above the thermometer bulb, and the lower end of the wick is immersed in distilled water. Separately, about 25 mm of moistened wick is exposed between the water and the bulb of the thermometer.
Those are two different measurements of two different parts of the wick. The first describes how far the wick reaches above the bulb. The second describes how much wet wick is exposed between the water and the bulb. Check both before the wait starts. A wick set up wrong means the 20-minute wait is spent on an instrument that is not set up the way the method expects, and you find out only after the crew has already started.
Some practical habits follow from the source. Keep distilled water on the truck, since the CCOHS description calls for distilled water, and do not assume the water in a site tap or a jug is suitable. Carry a spare wick and a clean container so a damaged set-up can be replaced without waiting for the next delivery. Ask whoever places the wet-bulb to check the wick length and the water level at placement, and to write that check on the log. A thirty-second check at the moment of placement costs less than a repeat of the whole wait.
Timing the reading into the schedule
The scheduling method is to work backwards from the moment a reading is needed. Start with the crew's start time, pick the reading time that must come before it, and then subtract at least 20 minutes once when both instruments are placed together, or from the later placement time when they are placed one after another, using the CCOHS minimum as the floor. The source gives 20 minutes as the least a reading needs, so the placement time on the board should always leave more room than that.
Write the placement time on the board as its own item, and write the earliest reading time beside it. The two times do different jobs. The placement time shows when the clock started. The reading time shows when the number becomes usable. Keeping both visible means nobody has to work out the arithmetic at the last minute with a crew waiting at the gate.
Illustrative example: a 7 am start
Suppose a crew is due to start outdoor work at 7:00 am, and the team lead wants the reading in hand before they begin. For a reading to be ready at 7:00 am after a 20-minute settle, the instruments need to be in place by 6:40 am. Because 20 minutes is a minimum, most dispatchers will do better to set the instruments out a little earlier than that. The extra margin covers a wick that needs adjusting, an instrument that has been knocked, or a crew that arrives at the site earlier than the board said.
Two more points belong in the plan. First, a reading describes the spot where the instruments stood. If the crew's work area is different from that spot, either take the reading from the new area or say clearly on the record which area it covers. Second, do not move the instruments during the wait. Moving them restarts the question of whether they have settled, so they may need their full wait again. If the work area changes mid-morning, treat the new area as a new placement with its own wait.
Who sets up, who reads, who decides
A heat check is easy to lose when nobody is clearly responsible for each part of it. A workable split puts three roles on the job record. The person who places the instruments owns the set-up and the placement time. The person who reads them owns the reading time and the values written down. The team lead owns the decision about what the reading means for the crew. These can be the same person on a small job, but the record should still show each step.
Dispatchers sit between these roles. Their job is to make sure a placement time exists on the board, that the reading is scheduled before the crew's start, and that the result reaches the team lead before work begins. A dispatcher does not need to interpret the numbers to do that job. A dispatcher does need to know who to call when a placement or a reading is late, because a late reading is the easiest way for a planned heat check to slip without anyone noticing. For the wider check before a crew leaves, see job site dispatch checks before crews leave.
The split should also show up in training. Anyone who will place or read the instruments should be shown the set-up on the actual kit they will use, including the wick and the water, and should practice the wait once before doing it on a live job. The first real placement is a bad time to learn where the distilled water is kept.
When no reading is ready at start time
Sometimes the clock runs out. The instruments were placed late, the wick needed a second set-up, or the crew arrived early. In that case the dispatcher's job is to report that the reading is not ready, not to fill the gap. Do not give the crew an older reading from another site or a previous day, and do not write a number into the record that nobody has taken. A reading describes the conditions when it was taken, and an old or guessed value describes nothing about the job in front of the crew.
The next decision belongs to the team lead and to the site's own procedures. Depending on how the job is set up, that might mean waiting for the reading, moving the start, or going ahead with a plan the team lead has already agreed for that situation. The dispatcher's part is to say what time the reading will be ready, if anyone knows, and to keep that time visible to the people who need it.
It helps to agree on this in advance. A short note on the dispatch board that says "heat reading not yet ready" is easier to act on than a silent gap that someone finds at the gate. Make it normal to say so early. A late reading that is reported early gives the team lead options that a missing reading discovered at the last minute does not.
Recording and handing off
Write every heat check down, including the ones that were late or that failed to happen. For each check, record the site, the spot where the instruments stood, the time they were placed, the time they were read, the values read, the person who placed them, the person who read them, and whether the reading came before or after the crew started. That list is short, and it turns a vague "we checked" into something a later shift can actually use.
Record the set-up as well. Note the wick length as it was set, and the water used. If a reading is questioned later, the set-up record is what shows whether the instrument was used the way the method describes, and it gives the next person a way to tell a sound reading from a doubtful one.
Keep the record with the job, not in someone's notebook. For a handoff format, see the Field Service Work Order Checklist for Dispatch Handoffs. If the job runs past a shift change, the incoming dispatcher or team lead should be able to see when the last reading was taken and where the instruments are now. Without that, the next person may plan the afternoon around a reading that describes the morning, or may repeat a wait that was already finished. A clear hand-off costs a minute and saves a second 20-minute wait.
Finally, review the records once a week or after any job where a reading was late. Look for the patterns. Were placements usually late on the same kind of job? Did the wick need redoing more often on one kit? Did any job run longer than the table's stated assumptions? Those answers point to the fix, whether that is an earlier placement time, better kit, or a conversation with the team lead about shift length. The two waits do not change. What changes is how early the plan starts the clock.
Next step for today
Today, pick the next outdoor job on the board and write its placement time on its own line, with the earliest reading time beside it.
Related guides: California outdoor heat rules: 3 duties for crews · California paid sick leave: 4 numbers for part-time techs · Check 4 leave counts before you approve time off.
Frequently asked questions
Can a reading taken before the instruments settle be used?
No. A reading taken before the instruments settle is not one you can rely on.
Do the two waits add up?
They add up only if the instruments are placed one after another. Placed together, the two waits run side by side.
Does a passed heat screen mean the work is safe?
No. A passed screen is a fast first check, not a guarantee, and dispatchers should not describe it as one.