A lien is a claim against property that secures payment for work or materials. Lien rules are set by each state. Washington is a useful example because its statute has a hard time limit and a separate notice rule for new houses.
The recording period
The Washington statute on recording a claim of lien says the period "is a period of limitation and no action to foreclose a lien shall be maintained unless the claim of lien is filed for recording within the ninety-day period stated" (RCW 60.04.091).
Two things stand out. First, this is a limitation period, so a claim filed late may not be enforceable no matter how reasonable the delay seems. Second, the window is measured in days, so a job that is closed on paper can still have an open window. Do not assume the count starts the day you close the file. Find the trigger in the full statute, and ask counsel to confirm it before you rely on it.
If your team relies on the recording window for collection, put the last day to file the claim of lien in the job file as a hard due date, computed from the trigger that counsel confirms. Record who is responsible for filing and how the claim was filed.
For dispatchers, the most useful habit is to make the last delivery date a required field in the job record, not a note in a text thread. The notice rule below depends on the dates materials and services were supplied, and the recording window runs from a trigger event that the full statute defines. If those dates are scattered across phone photos, paper tickets, and memory, the file will be hard to defend when someone asks for it.
Notice rules for single-family homes
Washington also has a separate rule for new single-family residences. According to RCW 60.04.031, for new construction of a single-family residence, the notice of a right to claim a lien "may be given at any time but only protects the right to claim a lien for professional services, materials, or equipment supplied after a date which is ten days before the notice is given" (RCW 60.04.031).
In plain terms, a late notice does not reach back to cover all of the work. That is why notice timing matters even after the job is physically done, and why the last delivery date should be easy to find.
The same section also says when a notice counts as received. It recognizes actual delivery by personal service or registered or certified mail, or three days after mailing by registered or certified mail, excluding Saturdays, Sundays, or legal holidays (RCW 60.04.031). Three practical points follow:
- For registered or certified mail, record both the mailing date and the date the notice actually arrived so either test can be checked.
- For personal service, record the date and the person who received it.
- Keep mailing records and tracking records for every notice, because the counting rule depends on the mailing date.
Lien checklist
- Record the last date materials or services were supplied, using delivery tickets and timesheets.
- Put every notice and recording date on the job calendar, with a named owner.
- Ask counsel whether the job is new construction of a single-family residence, since the notice rule above is specific to that situation.