An EPA lead firm certificate renews by applying 90 days before expiration, with the next term counted 5 years from the old expiration date. If your firm holds an EPA lead renovation certification, you already know it is not a one-time event. The certificate has an expiration date, and renewing it is a process with its own timing rules. Miss a step and the problem does not stay in the office file. It can show up on a job site, in the middle of a paint job, with a customer waiting.

Key takeaways

  • Submit a complete application, with the proper fee, at least 90 days before the current certificate expires.
  • Count back 90 days from the expiration date and set an earlier internal target.
  • The renewed certificate expires 5 years after the old expiration date, not after EPA approves it.
  • Amend your certification within 90 days of any change to information in your most recent application.
  • Assign one named person to own the renewal file and the calendar.

Federal law requires all renovation, repair, and painting firms (including sole proprietorships) working in housing, or facilities where children are routinely present, built before 1978, to be certified. That means the certificate is not just a concern for large contractors. A two-person shop that paints kitchens in older homes needs it too. The office lead who keeps the paperwork moving should know these deadlines as well.

This post walks through three deadlines that owners and office leads should put on a calendar as soon as they know the renewal is coming. Each one comes from EPA's firm certification guidance. Where a rule includes a number or a date, I quote it from EPA's page and link to it. Where I give advice that is not a rule, I say so. This is general information, not legal advice. If something here does not match what you see on EPA's site or in your own certification letter, trust the official source and ask EPA before you act.

The three deadlines are:

  1. The application window, which closes 90 days before your current certificate expires.
  2. The expiration date of the renewed certificate, which is counted from the old expiration date, not from the day EPA approves your application.
  3. The amendment window, which gives you 90 days to update your certification after something in your application changes.

Each one has a different kind of risk. The first can cause your certification to lapse. The second is easy to get wrong when you set your next renewal reminder. The third can stop your crews from doing renovation work even though your certificate is still valid on paper. Let's take them in order.

Deadline 1: The application must go in 90 days before expiration

The first rule is the one most firms know about, and it is also the one most often treated too casually. EPA's guidance says: You must apply for a re-certification at least 90 days before the firm's current certification expires.

Notice the word "apply." The rule is about when your application is submitted, not when EPA finishes reviewing it. EPA also explains what makes an application count on time. According to the same page, if a complete application, including the proper fee, is submitted 90 days or more before the date the firm's current certification expires, then the application will be considered timely and sufficient.

Two parts of that sentence matter for your calendar. The first is "complete." An application that is missing information is not the same as a complete one, and a submission that is incomplete may not get the protection the 90-day rule provides. The second is "the proper fee." A check that is missing, short, or sent to the wrong place can leave you in the same position as a late application. Before you submit, go through the full application against EPA's current requirements and confirm the fee amount on EPA's site.

How to count the 90 days

Counting back 90 days is simple arithmetic, but it is easy to get wrong when you are busy. Take the expiration date printed on your current certificate and count backward 90 days. Write that resulting date on the calendar in bold, and label it as the last day the rule supports for a submission to count as timely and sufficient. It is not a good target date.

Treat the 90-day mark as the deadline you must not miss, and set an earlier internal date for finishing the application. Many firms find it useful to pick a date that gives them a comfortable margin, such as several extra weeks, so there is room to gather documents, fix errors, and send the payment. The exact margin is your choice. The point is that the internal date should come before the EPA date, not on it.

If you are not sure how a date falls, do not guess. Ask EPA before the window closes. A question asked in time costs you a phone call or an email. A question asked after the deadline may cost you the certification.

What happens if you submit late

The timing rule has a second half, and it is the part that causes real trouble. EPA's page explains the situation for applications submitted too close to the expiration date. In those cases, if EPA does not approve the re-certification application before the existing application expires, then the firm's certification expires.

Read that sentence slowly. The protection that comes with a timely application does not apply when the application is submitted less than 90 days before the current certification expires. In that case, the firm is depending on EPA finishing its review before the existing certification runs out. If the review is not finished in time, the certification ends. The firm then has to deal with a lapsed certificate, which is a much bigger problem than a stack of paperwork.

For an owner, the lesson is straightforward. A late submission is a gamble on EPA's review schedule, and the firm carries all of the risk. The safer path is to submit early enough that the application counts as timely from the start.

A practical step for the office

Give one person responsibility for this deadline. In a small firm, it is easy for everyone to assume someone else is watching the expiration date. Name the office lead, or whoever handles licensing and recordkeeping, as the owner of the renewal file. Ask that person to confirm the expiration date in writing, set the internal target, and report back when the application has been sent. A short written note with the date and the method of submission is useful later if a question comes up. For crew planning around older homes, see our lead compliance program guide.

Deadline 2: The new expiration date is counted from the old one

The second deadline is about the date your renewed certificate will expire. It is easy to overlook because it does not feel like a deadline at all. It is a date you will need to know for the next cycle.

EPA's guidance on this point is specific. According to the firm certification page, the expiration date for the firm's re-certification will be 5 years from the date the existing certification expired, regardless of when the re-certification is approved.

That sentence contains two ideas that work against common habits. The first is that the new expiration is based on the date the old certificate expired. It is not based on the day your renewal was approved. The second is that the date stays the same even if approval comes late. The phrase "regardless of when the re-certification is approved" is the key.

Illustrative example: the math

Suppose your current certificate expires on June 1, and you file a complete application with the proper fee on March 3, which is 90 days before that date. If EPA approves it in October, the renewed certificate still expires on June 1, 5 years after the old date. The approval date does not change the end date.

This matters in two directions. If your team waits for the approval letter and then counts five years from that letter, the calendar you set will be wrong by months. Your next application window, which closes 90 days before the new expiration date, will also be wrong. A firm that plans its next application around a wrong date can miss the window entirely.

The second direction is about expectations. A late approval does not give you extra time on the new certificate, because the end date stays where it is. That is one more reason to focus on the first deadline.

Update the calendar as soon as you know the date

Once you have a renewal approval, write down the new expiration date in your records and in every calendar your team uses. Then work backward to set the next application window. Count back 90 days from the new expiration date, and set an internal target well before that mark.

Deadline 3: Amendments are due within 90 days of a change

The third deadline is the one most likely to catch a firm off guard, because it has nothing to do with the renewal itself. It applies whenever something in your application changes.

EPA's guidance sets the rule plainly. A firm must amend its certification within 90 days of a change to information included in its most recent application.

The rule has a consequence, and the consequence is serious. According to the same page, if a firm fails to amend its certification within 90 days of the date the change occurs, then it will not be authorized to perform renovations until its certification has been amended.

Read that twice. The risk is not only a note in your file. Your firm can be barred from performing renovations until the amendment is complete. Your certificate may still be valid on paper, your renewal may be on track, and your crews may still be scheduled for jobs. None of that changes the fact that the firm is not authorized to do the work until the amendment is in place.

What counts as a change

The rule applies to changes in information that appears in your most recent application. That wording means the first step is to know what your application says. Pull the most recent application from your records and read it line by line, item by item. Any detail that changes from what that application says needs to be amended. Check EPA's guidance to see exactly which information it covers.

The rule does not ask you to decide whether a change is important enough to report. It asks whether information in your most recent application has changed. Firms sometimes assume that small changes can wait until the renewal. That assumption can be expensive. If a change happened and you did not amend within 90 days, the consequence in EPA's guidance applies, and nothing in that consequence depends on how minor the change seemed to you.

An example of the 90-day window

Suppose a change occurs on January 1, which puts the amendment deadline 90 days later, on April 1. If your firm does not amend by that date, the firm is not authorized to perform renovations until the amendment is complete. The clock starts on the date the change occurs, not on the date someone notices it or the date you finally get around to paperwork.

That is why the amendment deadline should be tracked as a live item, not something you remember at renewal time. A change that happens in the middle of a cycle can easily be forgotten by the time renewal season comes around. By then, the window may have closed months earlier.

A simple way to catch changes

Create a short review habit for your firm. Once a quarter, or any time your office or staffing changes, the owner or office lead should check the most recent application against the current facts. Ask simple questions about each item in the application. Has anything that the application states changed since it was filed? Has a person the application relies on left or joined the firm? If the answer to any of these is yes, check EPA's guidance to confirm the requirement, and start the 90-day count.

Put the amendment date on your calendar, counted 90 days forward from the day the change occurred. For the older-home side of the job, see lead pamphlet checks before an older-home visit.

Putting the three dates on one calendar

  1. Write down your current expiration date. Count back 90 days to find the EPA application deadline. Set an earlier internal target, and assign one person to own it.
  2. Once you submit the renewal, record the date and method of submission. Keep a copy of the complete application and proof of payment with the file.
  3. When EPA approves the renewal, write down the new expiration date using the old expiration date as the starting point. Count back 90 days from the new date to set the next application window.
  4. Keep a standing review of your most recent application. When a change occurs, write down the date it happened and count forward 90 days for the amendment deadline.
  5. Review the whole calendar at least once a year, and again any time a key person leaves the firm. A calendar that only one person understands is a risk.

Common mistakes to avoid

Several errors come up again and again when firms talk about certification renewals. Watch for these in your own office.

Counting from approval instead of expiration. As EPA's guidance makes clear, the new expiration date is tied to the old one. If your calendar uses the approval date, the entire cycle will drift.

Keeping records in one person's inbox. If the only copy of the application, the proof of payment, and the approval letter lives in one email account, the firm is exposed when that person is out sick or leaves. Keep the files where the whole team can find them.

Keep your records in order

Good recordkeeping makes every deadline easier to meet. For each renewal cycle, keep a clear file that includes the complete application as submitted, proof of payment, any correspondence with EPA, the approval letter, and the current certificate. Add a running note for any change to the firm's information, with the date the change occurred and the date you amended the certification.

This file is also your evidence if a question comes up later. When someone asks whether your firm renewed on time, you want to answer from paper and dates, not from memory.

Your next step

If you take one thing from this post, let it be this: put all three dates in writing today. Find your current expiration date, count back 90 days, and assign the renewal to one named person. Then open your most recent application and check whether anything has changed since you filed it. If something has, start the 90-day count now. Your EPA guidance is the authority on every rule mentioned here, so read the official page before you act, and contact EPA when a date or requirement is unclear.

Related guides: Lead hygiene facilities: 8 items to set up for the crew.

Frequently asked questions

When is the renewal application due?

It must be submitted at least 90 days before the firm's current certification expires. Count back 90 days from the expiration date on your certificate to find the last day the rule supports.

Does the renewed certificate run 5 years from approval?

No. The re-certification expires 5 years from the date the existing certification expired, regardless of when EPA approves it.

How long do I have to amend after a change?

Your firm must amend its certification within 90 days of a change to information in its most recent application. If it does not, it is not authorized to perform renovations until the amendment is complete.

Sources

More field guides