2 consent thresholds for work near a low voltage line

WrenchQuarry Editorial Team · Published · 12 min read · How these guides are written

Two numbers, two different jobs

New Zealand guidance sets consent limits for low voltage overhead lines: no owner consent below 0.5 m, and conditional consent up to 4 m. Roof, scaffold and access jobs at customer properties often have one awkward feature: an overhead line close to the building. When that happens, the question is no longer only how to do the work. It is also who is allowed to say yes.

Key takeaways

  • Owner consent cannot cover work less than 0.5 m from the overhead line.
  • Between 0.5 m and 4 m, written consent applies only where temporary isolation of the supply is not reasonably practicable.
  • The trades agree between themselves who asks the owner before anyone approaches.
  • Ask about the line on the first call, and do not book a start date until the path is clear.

The guidance is published by WorkSafe New Zealand on its working near low voltage overhead electric lines page. It points readers to the full code for the detail. In its own words, "See Section 5 of NZECP 34 for the complete requirements." This post summarises the parts that affect booking decisions. It is not a replacement for the code, so treat it as a list of questions to ask, not as the final answer.

The two numbers do different jobs. The first sets a limit that owner consent cannot move. The second marks a zone where owner consent can be part of the route to doing the work, but only in a specific way. Mixing them up is the easiest way to end up with a signed form that does not cover the job actually being done.

The closest threshold is the simplest to state. The guidance says: "The property owner cannot give consent for work to be carried out less than 0.5 m from the overhead line." (Source)

That sentence closes off an option many people assume they have. Customers often say "it's my roof, I'll sign whatever you need." For work less than 0.5 m from the line, the guidance says that signature is not enough. The owner's goodwill does not change the answer, and neither does a longer conversation or a stronger assurance from the crew.

For dispatchers, this means a job that would bring the work closer than 0.5 m is not a paperwork problem to solve at the door. It is a job to re-plan. Before a crew is sent, the question to ask is simple: can the work be done without anyone working closer than that limit? If the answer is unclear, do not promise a start date.

Owners need the same message. If an owner asks whether they can approve close work to save a day, the honest answer is that the guidance says they cannot give that consent. Be direct about it. Saying "we'll see what we can do" invites the owner to try to sign something they have no power to sign.

The two thresholds side by side

The table below uses only what the guidance states. Read it as a sequence. The first row is a limit that owner consent does not reach. The second row is the band where owner consent becomes part of the route to the work, and only when temporary isolation of the supply is not reasonably practicable.

Distance from the overhead lineWhat the guidance saysCan the property owner consent?
Less than 0.5 mThe owner cannot give consent for work carried out at this distanceNo
Between 0.5 m and 4 m, where temporary isolation of the supply is not reasonably practicableWritten consent is needed for scaffolding erected close to the line and for the roofer to work in this bandYes, in writing, after the trades agree who approaches the owner

Source for both rows: WorkSafe New Zealand.

Reading the 4 m condition

Between 0.5 m and 4 m the picture changes. The guidance describes a route that does involve the property owner, but it is tied to a condition about isolating the supply. The relevant text reads:

> If it is not reasonably practicable for the electricity supply to the property to be temporarily isolated, they must agree on who will approach the property owner for written consent for scaffolding to be erected close to the overhead line and for the roofer to work between 0.5 m and 4 m from the line.

The source is the same WorkSafe New Zealand page. Three things in that sentence matter for booking.

First, the condition is practicality. The guidance does not say isolation is always required, and it does not say isolation is always possible. It says that where temporary isolation is not reasonably practicable, the consent route applies. Whether that condition is met is a question of fact for the particular job, and it should be answered before anyone relies on it. For a dispatch view of this question, see Scaffolding closer than 4 m to a line: when to isolate.

Second, the consent is written. A verbal okay from the owner is not what the sentence describes. Keep the written consent with the job record, and make sure it describes the scaffold and the roofer's work between 0.5 m and 4 m, not a general "go ahead".

Third, the people doing the work decide between themselves who will ask. The sentence says "they must agree on who will approach the property owner". That is a requirement, and it is easy to skip when two firms are booked by two different people who each assume the other has it covered.

Illustrative example: a roof edge 3 m from the line

A roof edge sits 3 m from a low voltage line. That is inside the 4 m band but outside the 0.5 m limit, so the owner route can apply if temporary isolation of the supply is not reasonably practicable. The first question is therefore whether isolation is reasonably practicable. If it is not, the trades agree who approaches the owner, and the written consent describes the scaffold and the roofer's work at that distance. If the planned route would take the roofer under 0.5 m from the line, the owner cannot consent to that part, and the plan must change.

Setting up the first call

Dispatchers usually hear about a job from the customer first, often as "we need a new roof" or "the gutters need doing". Those descriptions rarely mention the overhead line. So the first call should ask about it directly. Ask where the building sits in relation to the line, whether the line runs over the roof edge, along the wall where a scaffold would stand, or across the path a ladder would take. Photos help. A short site note such as "line runs along the back fence, about level with the eaves" is more useful than a general description of the property.

Then ask the question that decides which route applies: can the electricity supply to the property be temporarily isolated? The guidance makes practicality the test, so the answer should come from people who can judge it, not from a guess at the booking desk. Record the answer in the job file, along with who gave it and when. For a fuller checklist, see Overhead line checks: 8 items before dispatch.

Next, settle roles before anyone speaks to the owner. The guidance expects the trades to agree who approaches the owner for written consent. If one dispatcher handles both the roofing and the scaffolding, that person may be the natural choice, but the agreement still has to be made between the people doing the work, and it should be written down.

Last, do not book a start date until the path is clear. A crew that arrives to find a line closer than expected loses time and puts pressure on everyone to improvise on site. A short hold on the calendar costs far less than a rushed decision with a roof edge in front of you.

What to put in writing

The guidance refers to written consent, so the job file should hold one. Based on the sentence quoted above, a useful record includes:

  • The property address and the name of the owner who gave consent.
  • The work covered: scaffolding erected close to the overhead line, and the roofer working between 0.5 m and 4 m from the line.
  • Who asked for the consent, and who agreed to ask.
  • The reason the supply was judged not reasonably practicable to isolate temporarily, and who made that judgment.
  • The date the consent was given.

Keep the consent with the job record so the crew on site can see it. A consent that sits in someone's inbox does not help the person standing on the roof.

Do not ask an owner to sign a consent for work closer than 0.5 m. The owner cannot give that consent, so a form that tries to cover it is worth nothing and may create confusion later about what was agreed. If the work needs to go that close, the plan has to change.

What owners should hear

Owners often come to a job with their own picture of the risk. Many have lived under a line for years and feel they know it well. That experience is worth listening to, but the distances in the guidance do not depend on how familiar a line looks. A line can be closer to the roof than it appears from the ground, and a roof edge can sit nearer to a line than the owner expects.

When you explain the process to an owner, keep three messages simple. First, there is a distance below which they cannot give consent at all. Second, there is a band where they may be asked to sign, and that consent covers specific work described in writing. Third, the trades will agree between themselves who speaks to them, so the owner should not be surprised by two different callers about the same job.

Owners also have a practical stake in the site. Clearing the area under the work and keeping people away from it are matters the crew should set out before the day, not on the morning of it. This post does not list those arrangements, because they depend on the job. Ask the crew what they need from the property, and get the answer in writing alongside the consent.

Ladders and other access equipment

Not all access work is scaffolding. Ladders are common on residential jobs, and they bring their own risks near wires. The CCOHS guidance is direct on this point: "Keep ladders away from power wires, and if electricity is a hazard, a fibreglass ladder should be used." (CCOHS, portable ladders)

Two points follow from that advice. The first is that the instruction is about keeping the ladder away from the wires, not about how carefully the crew holds it. Distance comes first. The second is that the advice ties the choice of ladder to whether electricity is a hazard on the job. That judgment should be made before the ladder goes up, not halfway through the task.

For dispatchers, this means a ladder job near a line should carry a note that asks whether the crew has a fibreglass ladder available and whether anyone has assessed electrical hazards for that spot. For a ladder checklist, see Portable ladder safety: 9 reference points to check.

Common mistakes

A few mistakes come up often enough to name.

The first is treating the owner as the decision-maker for everything. Booking a crew on the strength of the owner's say-so, before checking the distance, is the mistake this post most wants to prevent.

The second is leaving the trades' agreement implicit. When the roofing and scaffolding firms each assume the other will contact the owner, the owner may receive no request at all, or two. Write down who is making the call and when.

The third is treating a consent as a permanent answer. A consent covers the work described in it. If the plan changes, for example if the scaffold position moves or the roofer's route changes, check that the written consent still matches the work before anyone starts.

The fourth is assuming a ladder choice is a minor decision. The CCOHS advice ties the choice of ladder to whether electricity is a hazard, so that judgment belongs in the plan, not in the crew's hands at the top of the ladder.

Where this guidance stops

This post covers two sources, and neither is the whole picture. The WorkSafe New Zealand page says that many of its definitions are based on other documents, including the Electricity Act 1992, the Electricity (Safety) Regulations 2010, the New Zealand Electrical Code of Practice for Electrical Safe Distances (NZECP 34), and AS/NZS 3000. It also states that "Electrical Safe Distances are specified in the New Zealand Electrical Code of Practice 34 (NZECP 34:2001)." (WorkSafe New Zealand)

The consent process itself is covered elsewhere in the same guide. The page says, "Section 10 of this guide has information about the consent process." Read that section before you draft a consent form, because the summary in this post does not describe the steps in full.

If you book work outside New Zealand, find the guidance from your own regulator and check the same questions: what the distance limits are, who is allowed to consent, and whether written consent is required. Do not assume the numbers in this post carry over to another country.

Finally, this post is practical guidance for planning, not legal advice. When a job is close to a live line, the safest first step is to stop, ask the questions above, and bring in people who can judge the site before anyone climbs, lifts or starts cutting.

Next step today

Before you book the next roof or scaffold job near a line, ask whether the electricity supply to the property can be temporarily isolated. Write the answer in the job file, along with the name of the person who judged it.

Related guides: Verify overhead line clearance: 4 checks before dispatch · Asbestos pipe amount: the 260-foot federal line.

Frequently asked questions

No, the property owner cannot give consent for work carried out less than 0.5 m from the overhead line.

It applies where it is not reasonably practicable for the electricity supply to the property to be temporarily isolated, and the trades have agreed who asks the owner.

Do ladders need a fibreglass ladder near a line?

Not always: the CCOHS advice says a fibreglass ladder should be used if electricity is a hazard, and ladders should be kept away from power wires.