Overhead rate for labor-hour bids: 2 totals

WrenchQuarry Editorial Team · Published · 12 min read · How these guides are written

To calculate an overhead rate for labor-hour bids, divide estimated overhead cost by estimated direct labor hours. The result is the amount they add for overhead on every hour a tech spends on a job. Some owners carry it over from last year. Others copy what a supplier or a friend says works. A few build it from the books. This post shows how to build it from the books, using just two totals.

Key takeaways

  • Divide estimated overhead cost by estimated direct labor hours for the same period.
  • Keep the cost list to costs you cannot trace to one job without guessing.
  • Count only hours a customer pays for, and write down how any other hours are treated.
  • Multiply the rate by a job's estimated labor hours to get the overhead that job carries.
  • At year end, compare the overhead applied to jobs with the overhead you actually spent.

This is for owners and office leads at small HVAC, plumbing, and electrical firms. If your estimator builds a bid from a labor hour count, the overhead line is the part of the price that gets the least attention. Labor hours and materials are easy to see on a job. Overhead is the rent, the insurance, the office phone, the truck payments, and the bookkeeper's time, and none of it lands on one job by itself. The overhead rate is how that shared cost finds its way into each bid.

Two totals, one division

The method has two inputs. The first is the total overhead cost you expect over a period. The second is the total direct labor hours you expect your techs to bill over the same period. Divide the first by the second and you get a rate per hour. Multiply that rate by the hours on a job and you have the overhead that job should carry.

The first total: overhead cost

Start with the overhead pool. This is every cost you cannot tie to one specific job without guessing. Keep the list short and honest. Rent for the shop and office, office salaries, software subscriptions, phone and internet, vehicle insurance and fuel for service trucks, tool replacement, and general liability premiums are common examples. Some owners also include the owner's own pay for office work, and some do not. Pick one rule and write it down, because the rate will only be as consistent as the list.

The list should cover the whole period you are pricing for, not just the busy months. A slow month can make the rate look high, and a busy month can make it look low. That is a reason to use a full year of expected costs and the same list every year, so you can compare them.

Keep the cost list clean

Most of the work happens before any division, and the cost list is where errors start. Go line by line through the last full year of your books and ask one question about each line: could this cost be traced to a single job without guessing? If yes, it belongs in job cost. If no, it belongs in overhead. For a layout of job cost lines, see the job cost sheet guide.

Some costs fall in between. Fuel for a service truck is a good example. You can estimate how much of each trip went to a particular call, but the estimate is still a guess. Decide how you will treat costs like that, write the decision down, and apply it the same way every year.

Watch for costs that are easy to forget because they are not paid monthly, such as annual license renewals, a yearly tool purchase, or a major truck repair. If the list only reflects monthly bills, the pool comes up short. Spread annual items across the full year so they show up in the rate in proportion.

The second total: direct labor hours

The second total is the direct labor hours you expect to bill for the period. These are the hours your field staff spend on customer work that can be traced to a job. A service tech who spends a morning on a no-cool call and an afternoon on a furnace install has hours that land on those two jobs. Time that does not go on a customer's invoice, such as loading the van or waiting on a parts run, is a different kind of cost, and your rules should say where it goes.

For a plain description of that work, the U.S. Department of Labor's O*NET OnLine summary for heating, air conditioning, and refrigeration mechanics and installers lists this task: "Install or repair heating, central air conditioning, HVAC, or refrigeration systems, including oil burners, hot-air furnaces, and heating stoves." That is the kind of field work that fills the direct labor column in an HVAC shop.

Choosing the hours you count

Count hours a customer pays for, and be clear about what else goes in. Shop time, training, and estimate visits are not the same kind of hour. Warranty work may be billed to a manufacturer or absorbed by the firm. Decide how each kind is treated, write the decision down, and keep it steady from year to year.

Hours usually come from a timesheet, a dispatch board, or job software that logs when a tech arrives and leaves a site. Check your source once against a few real jobs. If clock time runs much longer than the hours on the invoice, the gap tells you something about either the job or the timesheet, and you should know which before you trust the total.

Dividing the totals

The rate is the first total divided by the second. Write the division out with both inputs and the result, so anyone in the office can check it later. The textbook Principles of Accounting, Volume 2: Managerial Accounting walks through this method under the name traditional allocation method, and its example starts like this: "At the beginning of the year, the company estimates total overhead costs to be $2,500,000 and total direct labor hours to be 1,250,000." Those figures give a rate of $2.00 for each direct labor hour, which is $2,500,000 divided by 1,250,000 hours. (OpenStax) For a related walk-through, see the shop overhead rate guide.

Build one table you can reuse

A table keeps the math visible. Here are the figures from the textbook example in one place, so you can see how each one feeds the next:

ItemAmount
Estimated overhead costs$2,500,000
Estimated direct labor hours1,250,000
Overhead rate for each direct labor hour$2.00
Solo product direct labor hours350,000
Overhead applied to Solo product$700,000

Your shop's table would look the same, with your own totals in the first two rows. Keep each figure traceable to the one before it, so anyone checking the bid can follow the steps from the cost list to the price.

Applying the rate to a job

With the rate in hand, overhead for any job is the rate times that job's direct labor hours. The OpenStax example shows this for one product line. "For example, the total direct labor hours estimated for the solo product is 350,000 direct labor hours." Multiplying that by the rate, at $2.00 for each direct hour, gives $700,000 of overhead applied to the Solo product. (OpenStax)

For a service job, the unit is the job rather than the product. Estimate the labor hours, multiply by the rate, and that amount is the overhead the job carries. It goes into the price with the materials and labor you already priced. Then add the margin you want on top.

Keep one caution in mind. The overhead applied to a job is only as good as its hour estimate. An estimate that is far off moves overhead with it, so the estimator's hour count matters as much as the rate.

Illustrative example: a small shop

These figures are made up for illustration. Say a shop estimates $810 of overhead and 405 direct labor hours for the year. Dividing gives a rate of $2.00 for each direct labor hour. A job estimated at 4 labor hours then carries $8 of overhead, which goes into the price with materials and labor.

Turning hours into a flat price

The textbook takes one more step. It divides the overhead applied to the solo product by how many units it expects to make. Dividing the $700,000 by the estimated production of 140,000 units gives $5.00 of overhead for each unit of the Solo product. (OpenStax) A shop can use the same step with repeat work. If a standard tune-up takes the same number of labor hours every time, the hours for one visit times the rate gives a flat overhead amount for each visit, which is easier to put on a price sheet than an hour count.

Every shop's pool is its own

Each trade has its own heavy costs. A firm that stocks a lot of equipment, parts, or specialty tools will have a different pool than one that mostly bills time. Build the list from your own books, not from a trade average.

Choosing a period and sticking to it

Pick a period that matches how you bid. A full year is a sensible default, because it carries the seasons, the holidays, and the slow months together. A quarter can work if your business is very seasonal, but it needs the same care with the totals. Whatever you choose, use the same period for both totals. Mixing a yearly overhead figure with a monthly hour count would give a rate that looks reasonable and is not.

Checking the rate during the year

The rate is built from estimates, so actual numbers will drift. Compare your overhead spending and billed hours each month against the planned totals. If billed hours fall short of the estimate while overhead keeps running, the overhead applied to each job is too small to cover the cost. If billed hours run well above the estimate, the overhead applied will exceed what you spent. Neither is a crisis, but either is a reason to look at the totals again.

Update the totals when something real changes, such as a new lease, a larger office staff, or a different number of billed techs. Do not chase every small swing. A rate that changes every month makes past bids hard to compare with current ones. A common pattern is to set the rate once for the year, track the variance, and reset it when the next budget comes in.

When applied and actual overhead differ

At year end, compare two figures. The first is the overhead you applied to jobs, which is the rate times the hours you actually billed. The second is the overhead you actually spent. If the applied amount is lower, the shop carried cost that the bids did not recover. If it is higher, the bids recovered more than the costs that came in. Either way, the difference tells you whether the totals were close and whether the hours or the costs were off.

Do not hide the difference by quietly changing the rate mid-year. Note it, find the cause, and let next year's estimate reflect what you learned.

Common mistakes

Several errors show up again and again when small shops set this rate. The first is putting direct costs such as materials or field labor into the overhead pool, so the same cost is counted both in the job and in the rate. The second is leaving out a real cost, like office staff time or truck insurance, so the rate looks lower than it should. The third is counting hours that never reach a customer, such as shop time or training. That divides overhead by a bigger number than the jobs use, so the rate comes out too low.

The fourth is using last year's totals without a check. Costs change when you add a truck or move offices, and hours change when you add or lose a tech. A rate that was right two years ago can be wrong now.

Watch the rounding too. Rounding a rate to a whole dollar may feel tidy, but over a year of billed hours the difference adds up. Carry enough decimal places to keep the math honest, then round the price, not the rate.

Where the rate fits in the bid

A labor-hour bid usually has several parts. There is the labor for the job, estimated in hours and priced at what those hours cost you. There are the materials and any other direct costs. There is the overhead, which is the estimated hours times your rate. Together these make up the cost side of the bid, and the profit you want goes on top. If any part is missing, the bid can look fine on paper and still fail to cover the work.

Keep profit out of the overhead rate. The rate is meant to recover what it costs to run the business, not to set the margin. If you bury profit inside overhead, you lose the ability to see how much each job really contributes.

Share the rate with your team

The rate works best when the people who use it understand it. Estimators need to know what the overhead line covers and that it moves when the totals move. Techs do not need the math, but they should know that the hours they log feed the rate. When hours are logged in the wrong place, the error carries into the next round of bids.

A one-page sheet works well. It can list the overhead pool, the hour count, the rate, and the date it was set. Post it where estimators can see it, and keep old versions so you can see which rate a past bid used.

What the rate cannot do

A rate tells you what overhead to load on a job. It does not tell you whether the price is right. A rate can be perfectly calculated and still lead to a losing bid, if labor hours are underestimated, materials are priced low, or the market will not pay the full amount. Treat the overhead rate as one input, check the full bid against what the job actually cost, and compare your results to your own history.

Where to start

Here is a simple order to work in:

  1. Pull the last full year of overhead costs and sort each one as overhead or job cost.
  2. Count the direct labor hours for the same year, leaving out shop, training, and admin time.
  3. Divide the first total by the second and write down the rate with both inputs.
  4. Apply it to three recent jobs and compare the overhead with what you expected.
  5. Set a date to revisit the totals.

Two totals are enough to start. Once you have them, the overhead rate gives you a number you can explain to a customer and check against the books. Start with the books you already have, and do not wait for a perfect system. Your next step today: follow step 1 and pull last year's overhead costs from your books.

Related guides: Job-cost comparisons: 3 checks across periods · Overhead line checks: 8 items before dispatch.

Frequently asked questions

What is the overhead rate? The overhead rate is the estimated overhead cost divided by the estimated direct labor hours for the same period.

Should I reuse last year's totals? Not without checking them first.

Does profit go into the overhead rate? No. The rate is meant to recover what it costs to run the business, not to set the margin.