3 repair warranty terms: 1 year, notice, remedy

WrenchQuarry Editorial Team · Published · 12 min read · How these guides are written

Under FAR 52.246-21, a construction warranty runs for one year from final acceptance or earlier Government possession, requires written notice within a reasonable time of discovery, and obliges you to remedy any defect at your own expense.

  • The one-year clock starts at final acceptance, Government possession before final acceptance, or the repair or replacement date for work already fixed under warranty — not the invoice date.
  • Notice must be in writing and within a reasonable time after discovery, sent to a named person in your office; follow every phone callback with a same-day email.
  • You must remedy defects in equipment, material, workmanship, or design at your own expense, including when a subcontractor or supplier is at fault.
  • If you fail to remedy within a reasonable time after notice, FAR 52.246-21 lets the Government replace, repair, or otherwise remedy the problem at your expense, and an owner contract may grant an equivalent right.
  • Keep a job file with the acceptance date, notice log, written replies, diagnosis notes, repair records, and supplier notices — it's what wins a dispute.

The three terms you deal with on every callback

A customer calls about work you finished last spring. What you owe them, and what you must do about it, comes down to three terms: how long the warranty runs, how notice must be given, and who fixes the problem at whose expense.

Even if your job isn't a federal one, this clause is the cleanest statement of how these three terms fit together. Owner contracts may use similar terms, but each one has to be read on its own. Your own written contract controls your specific job, but the structure below tells you what to look for.

Here is what each term does, in plain language, and where the practical traps sit for a dispatcher or owner who answers the phone.

How long the warranty runs: the one-year clock

The base warranty runs one year. The clause states the clock starts at final acceptance of the work: "This warranty shall continue for a period of 1 year from the date of final acceptance of the work."

Final acceptance is not the day you finished the job. If an inspection, punch list, or sign-off stands between you and that date, your clock hasn't started yet.

There is a second starting point worth knowing. FAR 52.246-21 also starts the clock at Government possession if the Government takes possession of part of the work before final acceptance; whether an owner's early possession does the same depends on what your contract says. Hand over a section early and you start the year sooner than you planned.

Repairs get their own clock. Work you fix under warranty runs for a year from the date you completed that repair or replacement. So a job can have two live warranties at once: the original for untouched work, and a fresh year for what you redid.

Why this matters at the front desk: when a caller says "you did this eleven months ago," you need to check your records for the acceptance or possession date, not the invoice date. Write the acceptance date in the job file the day you get it. Two months later, nobody will remember it.

What the warranty covers is broad. The contractor warrants that the work conforms to contract requirements and is free of defects in equipment, material, or design furnished, and free of workmanship defects by the contractor or any subcontractor or supplier at any tier. Later in the same clause, the covered problems are listed as any defect of equipment, material, workmanship, or design.

In your terms: if the part was bad, the design was wrong, the material was wrong, or the install was done wrong, it counts — even if a subcontractor or your supplier caused it. You may have a claim against your supplier under their warranty, but that doesn't change what you owe the owner.

Here is how the main clock options compare:

Warranty scenarioClock starts onRuns for
Standard acceptanceDate of final acceptance1 year
Government possession before final acceptance under FAR 52.246-21Date the Government takes possession1 year
Work repaired or replaced under warrantyDate of repair or replacement1 year

Written notice: the step that makes it official

The second term is notice. The Contracting Officer must notify the contractor in writing, within a reasonable time after discovering any failure, defect, or damage.

Three things are doing work in that sentence.

In writing. A phone call starts a conversation. Written notice starts a record. What counts as written notice depends on the notice clause in your contract, so check it or ask your attorney. If you take a callback by phone, follow up with a short email restating what the customer reported and your proposed next step. That email is your proof the clock started, or that it didn't.

Within a reasonable time after discovery. The clock for giving notice starts when the problem is discovered, not when it is finally diagnosed. A leak seen in January but reported in June may raise a notice problem, depending on the facts. What counts as reasonable varies by the work and the facts, so put your own operating rule in place: log every report the day it comes in, with who called and what they said.

To the right person. Notice goes to the contractor. On your side, that means a named person in your office. If nobody owns the inbox, a notice can arrive and sit unread. Assign one address or one person for warranty notices, and check it daily.

Notice quality matters as much as timing. A useful notice identifies the job, the date of acceptance, what failed, and where. When you get one, reply in writing acknowledging it and stating your planned response. That sets your own timeline and shows you acted promptly.

On your side, your contract may require you to notify your supplier or subcontractor when their work or product is at fault. Do that in writing too, and do it fast. The FAR clause puts the burden on you to enforce downstream warranties for the government's benefit if the Contracting Officer directs it. Your owner contract may have a similar clause. So when a pump from your supplier fails on a job, you may need to press the supplier's warranty yourself while also making the owner whole.

If you have questions about what your own contract requires for notice — the form, the address, or the timing — ask the party who issued the contract, or your attorney. That is the one open point these general rules can't settle for you.

Who fixes it, and who pays

The third term is remedy. The clause says the contractor must remedy at the contractor's expense any failure to conform, or any defect. In practice: your cost, your labor, your materials. No invoice to the owner for the repair work itself.

That applies even when the original job was done correctly but a supplied part failed. The warranty covers defects in equipment, material, workmanship, and design, so a bad part is your problem to make right.

What about access, permits, and site protection? The clause doesn't itemize those, and your own contract or the owner's site rules usually govern. Read your contract for that question before you promise anything over the phone. In general, plan to cover your own mobilization for warranty visits.

There is a deadline on your side of the remedy too. If you fail to remedy any failure, defect, or damage within a reasonable time after the notice is delivered, FAR 52.246-21 gives the Government the right to replace, repair, or otherwise remedy the problem at your expense, and an owner contract may grant an equivalent right. So a slow response doesn't avoid the cost. It hands the job to someone else and still bills you.

Reasonable time is fact-specific. A burst pipe on an active site is not the same as a hairline crack in finished work. A practical pattern: acknowledge in writing the same day, inspect within a few days for urgent items, and schedule non-urgent fixes with a date you can keep. Then keep that date, or send a written update before it passes.

There is also a clause requiring you to enforce all warranties for the benefit of the Government if the Contracting Officer directs it. If your project has that kind of instruction, treat it as a work order: chase the supplier, document what you did, and keep the owner informed.

Handling the first callback call

The first call sets the tone and builds your record. Here is a simple way to run it.

  • Confirm the job. Get the job number, your acceptance date, and the caller's contact details before anything else.
  • Listen for scope. Note what failed, when it was noticed, and whether it is the original work or something you already repaired.
  • Check the clock. If the problem is within a year of acceptance or possession, the warranty clock is still running. Coverage also depends on whether the defect falls within the warranty and whether notice was given within a reasonable time. If you repaired it before, check the date of that repair.
  • Set the next step in writing. Send a short email the same day: what they reported, your planned inspection or fix, and the date.
  • Log the notice. Put the date, the discovery date they gave you, and their description in the job file. That file is what protects you later.

Keep your language factual. "Thank you for the notice, received today. We will inspect and confirm a date." That line, sent in writing, protects you and reassures them.

Running the repair without losing the warranty

Once a warranty repair is scheduled, three habits keep it clean.

First, diagnose before you promise. Look at the work, then tell the customer what you found. If the cause is unclear, say you are still checking. A promise you walk back is worse than a careful first answer.

Second, document before and after. Photographs, part numbers, and the old part if it came out. If the failure came from a supplier's product, that evidence supports your downstream claim while you still fix the owner's problem.

Third, close the loop in writing. When the repair is done, send a note: what you did, when, and what the warranty looks like now. That starts the new year for repaired work from the date of repair or replacement, and it gives the customer a clear anchor for the next call.

After a repair, the owner has a fresh year on that piece of work, and the untouched original work still runs on its original clock. Two clocks, one job file. Keep them both visible in your notes so the next dispatcher can see them at a glance.

Handling disputes and escalations

Some calls will not close neatly. Here is how to keep the situation steady.

If the customer's report is late — months after acceptance, with no prior notice — put your timeline in writing. State the acceptance date, the date you first heard about the problem, and that you are reviewing the report. Then get advice from your attorney before you commit. Reasonable time is judged on the facts, and your file is what proves them.

If the customer asks for work outside the original scope, treat it as a separate request. Warranty covers failures in the work you did. New wants, changes, or additions are a new conversation with a new price.

If your supplier is the cause, keep two tracks running. Track one: the owner's repair, on your schedule, at your cost. Track two: your claim against the supplier, with evidence and written notice. Never tell the owner to deal with your supplier directly unless your contract says so.

If the owner starts a third party to fix the problem, you may get billed. Your protection is speed and documentation: respond to notices promptly, offer a date, and keep proof you did. If you see that path coming, get advice from your attorney.

What your job file needs to hold

A warranty dispute is won or lost in the file. For each job, keep these items together:

  • Signed acceptance or possession record. The date that starts your one-year clock.
  • Notice log. Every report, with dates, who called, and what they said.
  • Written replies. Your acknowledgments and proposed dates, sent the same day.
  • Diagnosis notes. What you found, with photos and part numbers.
  • Repair record. Date of each repair or replacement, which restarts the clock on that piece.
  • Supplier and subcontractor notices. Copies of anything you sent to enforce downstream warranties.
  • Invoices and costs. Your costs on warranty repairs, since you bear them.

Store this where any dispatcher can reach it. A shared job folder or your system's job notes beat a paper binder in a truck. The goal is simple: anyone picking up the phone can answer "when did we accept this, and when did we hear about the problem" without digging.

Three common callbacks and how they play

The slow leak. Caller reports a stain on a ceiling, work accepted in winter, call comes in spring. Notice came soon after the stain was seen, so you inspect. If the cause traces to your workmanship, you repair at your cost. Photograph everything, log the repair date, and note the new clock on that section.

The noisy unit. Caller says a unit you installed runs loud. Acceptance was recent. You inspect and find a supplier defect in the equipment. You still fix or replace at your cost, because the warranty covers defects in equipment. Then you pursue the supplier separately, with written notice and your evidence.

The late report. Caller reports a crack, work accepted long ago, first time you have heard of it. You acknowledge in writing, state the dates from your file, and review whether notice came within a reasonable time after discovery. If the file shows an earlier report you can find, the picture changes. Get advice from your attorney before you decline or accept.

FAQ

Does the one-year warranty start on the day I invoiced the job? No. Under FAR 52.246-21 it starts on the date of final acceptance, or on the date the Government takes possession of part of the work if that happens first. If you already repaired part of the job under warranty, that repaired section runs a year from the date of that repair or replacement.

Is a phone call enough to start the notice clock? The clause requires notice in writing, within a reasonable time after discovery. A phone call is useful, but your record should show a written notice. Take the call, then send a short email the same day so both sides have the same record.

What if my supplier's part caused the failure? You still remedy at your expense for the owner, because the warranty covers defects in equipment, material, workmanship, and design, including work by subcontractors or suppliers at any tier. Then pursue your supplier's warranty yourself, in writing, with your evidence.

How fast do I have to fix something after notice? The clause says you must remedy within a reasonable time after getting the notice. If you don't, FAR 52.246-21 lets the Government replace, repair, or otherwise remedy it at your expense, and an owner contract may grant an equivalent right. Set your own response targets, acknowledge the same day, and keep to the dates you promise.

Does the warranty cover new work I choose to add? No. The warranty covers failure to conform to the contract and defects in the work you agreed to do. Add-ons, changes, and new requests are separate work, quoted and agreed on their own.

Who enforces a supplier's warranty for the owner's benefit? Under the FAR clause, the contractor enforces all warranties for the benefit of the Government if the Contracting Officer directs it. In your own contracts, look for a similar clause.