The second term is notice. The Contracting Officer must notify the contractor in writing, within a reasonable time after discovering any failure, defect, or damage.
Three things are doing work in that sentence.
In writing. A phone call starts a conversation. Written notice starts a record. What counts as written notice depends on the notice clause in your contract, so check it or ask your attorney. If you take a callback by phone, follow up with a short email restating what the customer reported and your proposed next step. That email is your proof the clock started, or that it didn't.
Within a reasonable time after discovery. The clock for giving notice starts when the problem is discovered, not when it is finally diagnosed. A leak seen in January but reported in June may raise a notice problem, depending on the facts. What counts as reasonable varies by the work and the facts, so put your own operating rule in place: log every report the day it comes in, with who called and what they said.
To the right person. Notice goes to the contractor. On your side, that means a named person in your office. If nobody owns the inbox, a notice can arrive and sit unread. Assign one address or one person for warranty notices, and check it daily.
Notice quality matters as much as timing. A useful notice identifies the job, the date of acceptance, what failed, and where. When you get one, reply in writing acknowledging it and stating your planned response. That sets your own timeline and shows you acted promptly.
On your side, your contract may require you to notify your supplier or subcontractor when their work or product is at fault. Do that in writing too, and do it fast. The FAR clause puts the burden on you to enforce downstream warranties for the government's benefit if the Contracting Officer directs it. Your owner contract may have a similar clause. So when a pump from your supplier fails on a job, you may need to press the supplier's warranty yourself while also making the owner whole.
If you have questions about what your own contract requires for notice — the form, the address, or the timing — ask the party who issued the contract, or your attorney. That is the one open point these general rules can't settle for you.