The federal clause sets three things a schedule of values for a multi-visit job should show: a value for each major activity needed to finish the work, all direct and indirect costs built into those values, and enough detail that the person paying can check each payment request. The federal construction clause GSA 552.236-15, Schedules for Construction Contracts sets out those same requirements and adds rules on how activities are sized and timed.
| Required item | What the payer asks | Clause basis |
|---|---|---|
| A value for each major activity | What is being paid for? | Assigning values to each major activity necessary to complete the work |
| All direct and indirect costs in those values | Whether the total is complete | Values must include all direct and indirect costs |
| Enough detail to check each payment | Whether a specific payment can be verified | Sufficient detail to enable the Contracting Officer to evaluate applications for payment |
The clause is written for federal construction contracts, so it does not govern a repair invoice or a residential install by its own force. Its logic still fits any job billed in parts, because a multi-visit bill is only as useful as the lines it is built from. Each of the three items answers a different question a payer will ask. The first asks what is being paid for. The second asks whether the total is complete. The third asks whether a specific payment can be verified. The sections below take each item in turn, then cover the rules on activity size and duration that sit alongside them.