The first step comes from section 34 of New Zealand's HSWA, titled "PCBU must consult other PCBUs with same duty." The WorkSafe New Zealand working-at-height page links to that section, and the rule applies in New Zealand. Elsewhere, treat the conversation as a sound habit rather than a requirement these sources set.
Start the talk with the work itself. Ask what the other crew will be doing, on which days, in which parts of the site, and at what times of day. Ask which tasks overlap with yours. One crew working below the other is an overlap. So is both crews needing the same access route, lift point, or storage area. Ask what equipment and materials they will bring into shared space, and whether any of it will stay there overnight. Send the answers to the other contractor, so both supervisors work from the same notes instead of from memory.
A shared plan does not need to be long. One page can cover the tasks each crew will do and when, the access routes and gates, the lift points and storage areas, the names and phone numbers of the people in charge, and the date of the last update. Put a date on it every time it changes. Without one, nobody can tell whether the copy on the gate matches the plan the supervisors approved.
Ask whether the other crew's workers know what your crew will be doing and when. A supervisor may have the full picture while the people on the ground have only part of it. Brief your own crew leads on the other crew's plan, and ask them to report anything that does not match. Crews often see an overlap forming before anyone in an office does, so they should know who to call and feel free to call without waiting for a meeting.
When you talk with the other contractor, a few questions help. Who is the point of contact for each crew? What hours will each crew work? What happens if one crew runs late and the other is already scheduled into the shared area? Who decides when a shared area is clear for the next task? You will not get every answer in one meeting. Note the open questions, put a date beside each one, and pick them up at the next talk.
If the other contractor is slow to reply, say so in writing and name a date for the next talk. Silence is not agreement, and a plan one side never acknowledged is a weak plan on a busy day.
Owners can help here. An owner who sets up the first meeting and names one person to keep the shared notes current removes the guessing about who runs the schedule. That person does not need to be a dispatcher, but they do need the authority to call a pause when the plan stops matching the site.
Expect the first talk to surface disagreements. Two supervisors who have run their own jobs for years may see sequencing, cleanup, or barrier placement differently. Those differences are easier to settle at a planning meeting than in the middle of a lift. Bring them out early and capture the decision reached.
Dispatchers can add a short check at the start of each shift: has anything changed since the last talk? A plan made at the start of a week can shift by midweek when a delivery moves, a second crew arrives, or a task runs long. Agree in advance on what counts as a change worth a phone call, such as a new lift, a new crew member on site, a different access route, or a delay that moves one crew into the other's area.
The same page also points readers to section 46 of HSWA, "Duties of other persons at a workplace" and to section 2.6 of its guidelines, "Worker engagement, participation and representation." Review both with your crew leads before the first shift. The page gives only these section titles, so build the conversation around what your own crews need to know rather than around details the sources do not provide.