When a job changes hands, the trucks, the crew, and the fence line may look the same to the neighbors. The stormwater paperwork, though, follows whoever is running the site. Under the EPA's Construction General Permit, coverage belongs to the operator.
The EPA's answer on operator changes is direct. When the site's operator changes, the new operator must submit a new NOI, and the previous operator must submit a Notice of Termination (NOT) as specified in Part 8.3 of the permit. (EPA's operator-change answer)
That is two filings for one handoff, and each belongs to a different party. The most common trap is treating the handoff as a single event. The outgoing contractor assumes the job ends when the equipment leaves. The incoming contractor assumes the file came with the job. Neither assumption opens the new filing or closes the old one. Each form needs an owner, and that owner should be a named person.
The gap between the two filings is where trouble usually starts. If the new operator's NOI lags, the paperwork may show nobody covering work that is still happening on the ground. If the old operator files its NOT before its areas are ready, the paperwork may release ground that still needs attention. Both problems come from the same habit: treating the handoff as a day on the calendar instead of a set of steps with owners.
The EPA answers quoted in this post concern the 2017 Construction General Permit. If your site falls under a different permit, or under a state program with its own forms, the names and steps can differ. Read the permit that covers your site before you act on anything here.