2 notices when a site changes operator: NOI and NOT

WrenchQuarry Editorial Team · Published · 11 min read · How these guides are written

Why a handoff needs paperwork

When a job changes hands, the trucks, the crew, and the fence line may look the same to the neighbors. The stormwater paperwork, though, follows whoever is running the site. Under the EPA's Construction General Permit, coverage belongs to the operator.

The EPA's answer on operator changes is direct. When the site's operator changes, the new operator must submit a new NOI, and the previous operator must submit a Notice of Termination (NOT) as specified in Part 8.3 of the permit. (EPA's operator-change answer)

That is two filings for one handoff, and each belongs to a different party. The most common trap is treating the handoff as a single event. The outgoing contractor assumes the job ends when the equipment leaves. The incoming contractor assumes the file came with the job. Neither assumption opens the new filing or closes the old one. Each form needs an owner, and that owner should be a named person.

The gap between the two filings is where trouble usually starts. If the new operator's NOI lags, the paperwork may show nobody covering work that is still happening on the ground. If the old operator files its NOT before its areas are ready, the paperwork may release ground that still needs attention. Both problems come from the same habit: treating the handoff as a day on the calendar instead of a set of steps with owners.

The EPA answers quoted in this post concern the 2017 Construction General Permit. If your site falls under a different permit, or under a state program with its own forms, the names and steps can differ. Read the permit that covers your site before you act on anything here.

The new operator's NOI

The NOI is the form that brings the incoming operator under permit coverage. The EPA says operators must use its NPDES eReporting Tool (NeT) to prepare and submit NOIs under the 2017 CGP, unless they receive a waiver from their EPA Regional Office. (NeT rules in EPA guidance)

ItemRuleApplies to
Filing routeNeT electronic submission2017 CGP NOIs
Waiver optionWaiver from EPA Regional OfficeNeT requirement
Copy requirementCheck Part 9 for state or Indian tribe copiesAll NOIs
Original NOI timingNo later than 30 calendar days after commencing constructionOriginal NOIs
Operator change timingNo day count given in the EPA answerOperator handoffs
SourceEPA—

For a takeover, that means the incoming company needs working NeT access, and at least one person who can log in, before handoff day rather than on it. A waiver is an exception you have to actually receive. Do not assume you have one.

The EPA also points to Part 9 of the permit. Operators must check there to see whether copies of the NOI must go to a state or Indian tribe. (EPA guidance on Part 9) Read that section for the specific site rather than relying on what you remember from the last job. The answer depends on where the site sits and what the permit requires. A copy sent to the wrong office is one more thing to fix during a busy handoff.

Timing needs care. For an original NOI, the EPA's answer is no later than 30 calendar days after commencing construction activities. (EPA's timing answer) The answer on operator changes gives no day count for the new operator's filing. So do not assume the 30-day figure carries over to a takeover. Confirm the timing in the permit text, and plan the filing so it does not depend on a guess.

Comparing the two notices

The table below compares what the quoted EPA answers say, row by row. It covers the 2017 CGP only.

ItemNew operator: NOIOutgoing operator: NOT
FormNotice of Intent (NOI)Notice of Termination (NOT)
Who filesThe new operatorThe previous operator
Trigger in the EPA answersA change to the site's operatorAll covered construction activities are eligible for termination under Part 8
Timing givenNo later than 30 calendar days after commencing construction (original NOI)Submitted in accordance with the permit once eligible
Filing routeThrough NeT, unless the EPA Regional Office grants a waiverWhere the permit specifies it: Part 8.3
Other checkPart 9, for copies to a state or Indian tribeConfirm the termination requirements in Part 8

Read across the rows and the forms answer different questions. The NOI answers who is covered now. The NOT answers who is released, and when. On a handoff, different people often handle those questions, which is why each one needs an owner.

The outgoing operator's NOT

The outgoing operator files the NOT once the work it covered is ready. The EPA says that once all construction activities included in the original NOI are eligible for termination of coverage under Part 8 of the CGP, the operator must submit the NOT in accordance with the permit. (EPA's termination answer)

TopicRequirementPermit reference
Filing triggerAll covered construction activities eligible for terminationPart 8
Form locationNOT filed as specifiedPart 8.3
Stabilization testFinal stabilization on all areas not covered by permanent structures2017 CGP
Control conditionAreas the operator controlled during construction2017 CGP
Additional conditionsOther termination requirements must be met2017 CGP
SourceEPA—

Because the EPA answer sends you back to the permit for the mechanics, read Part 8 before the NOT is drafted, not after. The termination conditions are easier to check against the permit text than against anyone's memory of them, including the memory of the crew lead who ran the job.

The EPA also explains when that point arrives for stabilization. Under the 2017 CGP, an operator can terminate coverage once final stabilization has been achieved on all areas not covered by permanent structures that the operator controlled during construction, provided the other termination requirements have been met. (EPA's stabilization answer)

Two practical points follow from that wording. First, the test is written around the areas the outgoing operator controlled. If the site was split, with one contractor finishing one area and another taking over the rest, the control line decides whose stabilization counts toward whose NOT. Put that line in writing before anyone leaves. Second, leaving the site does not make a NOT eligible by itself. Eligibility depends on the stabilization and other requirements the permit describes, not on the day the last crew drove out the gate.

Before the handoff day

Start by pulling the original NOI and making sure both parties have a copy. The outgoing contractor needs it to know what was filed. The incoming contractor needs it to see what coverage they are replacing. A copy that exists only in one person's email becomes a problem during a dispute, a site visit, or a staff change.

Checklist stepPurposeOwner
Pull the original NOIBoth parties see what was filedBoth parties
Agree on the splitRecord which areas each party controlsBoth parties
Confirm NeT accessIncoming team can log in before filing dayIncoming operator
Get stabilization statusArea-by-area status for the NOTOutgoing operator
Check Part 9Identify state or tribal copy requirementsFiling owner
SourceEPA—

Next, agree on the split. Write down which areas each party controls and the date control moves from one to the other. Initial the note so it is clear the split was agreed, not assumed. Later, this note is what tells you whether the old contractor's NOT matches the ground it covers.

Confirm the incoming company's NeT access now. Check that someone on the new team has a login, that the account is current, and whether a waiver would be needed for any reason. Do not wait for the filing day to find out that nobody can sign in.

Ask the outgoing contractor for stabilization status area by area. Walk the site or get dated photos. The NOT depends on final stabilization in the areas that party controlled, so a general statement that the work is done is not enough to file on.

Finally, check Part 9 for any state or tribal copy requirement, and assign each filing to a named person. Companies do not file forms. People do.

Caltrans's construction manual shows why a checklist should look past the obvious permit. In its safety section, it sends readers to another chapter for a separate subject: "Refer to Chapter 7, “Environmental Stewardship,” of this manual for additional guidelines on hazardous waste." (Caltrans construction manual, safety section) Stormwater is rarely the only environmental obligation on a job site. A handoff checklist should name every chapter and permit that governs the work, not just the one you came to check.

Who owns the handoff

On many jobs, the owner and the dispatcher are the two people who see a handoff coming. The owner usually decides when the site changes hands and what the contract says about responsibilities. The dispatcher usually knows which crew is on site, when they leave, and when the next crew arrives. Those two views are useful together, and they often go missing when the paperwork is treated as a field detail.

The owner's job is to make sure the contract or handoff agreement names who is responsible for stormwater coverage during the change. If the agreement says nothing about it, nobody has agreed to file, and both forms can end up unowned. 558.004) governs notice of those claims in Florida only, and it serves as an analogy here rather than a general rule. Florida's statute on construction defect claims says: "If the construction defect claim arises from work performed under a contract, the written notice of claim must be served on the person with whom the claimant contracted." (The Florida Senate, s. 558.004) That law covers a different subject than stormwater, but the principle carries over. Notice goes to the party you actually contracted with. A handoff agreement should be just as specific about which party owns each filing.

A useful handoff agreement names each party, lists the areas each one controls, gives the handoff dates, and says who receives copies of both forms. It should also give a contact for each company after the crews have gone, since questions about the site tend to arrive weeks later. The owner can ask for copies of both forms and a short written confirmation that each filing is complete.

The dispatcher's job is timing. Put the handoff date on the calendar with the NOI and NOT steps beside it. If the outgoing crew is scheduled to leave before stabilization is complete on their areas, raise that before the crew is pulled, not after. A dispatcher who can see both schedules can often prevent the gap.

Keeping the paper trail

Keep the file in one place the site team can reach. That means the original NOI, the new NOI as submitted, the NOT as submitted, the split-of-control note, and any state or tribal copies identified in Part 9. If the site is inspected or a neighbor complains, the first question will be who was responsible for what, and on which date. A folder that answers that in one look saves a lot of time.

For each filing, note the submission date and the method. The EPA says NeT is the required route for NOIs unless a waiver applies, so the file should show whether the filing went through NeT or under a waiver.

The file matters after the job closes, too. Questions about past work can come up long after the NOT is filed, from an inspector, a neighbor, a new owner of the land, or a future contractor who inherits a related job. Store the file where the next dispatcher or owner can find it, not in one person's inbox. Note who held the paperwork at each stage, so the trail still makes sense after staff changes.

Takeovers in the middle of a phase

Many handoffs do not happen at the start or end of a job. A contractor may be pulled off a site partway through grading, with some areas stabilized and others still bare. In that case the NOT question is not "is the job done?" It is "which areas are finished under the permit test?" The EPA language on termination points to final stabilization on the areas the operator controlled, so a mid-phase handoff needs a clear map of those areas.

Ask for that map before the handoff. A simple sketch with area names, the date each area was stabilized if it was, and the person who controlled it at the time can be enough to start. It turns a vague status into something the outgoing operator can check and the incoming operator can rely on.

Expect that some areas will be ready and others will not. That is normal. The outgoing operator's NOT waits until the covered work is eligible under the permit, and the split note records which party controls each area while the permit's termination test applies to the outgoing operator's areas. If the split is clean, the forms line up with the ground. If it is not, stop and sort it out before anyone signs. A filing that does not match the ground is much harder to correct after it goes in.

Closing note

A site change is one event with two filings. The incoming operator files a NOI, the outgoing operator files a NOT, and each form depends on the other being done right. The EPA's answers give the core rules: a new NOI from the new operator, a NOT from the previous operator under Part 8.3, NeT for NOI submission unless a waiver applies, and termination once the permit's stabilization and eligibility requirements are met. (EPA guidance)

Plan the handoff so both forms have an owner, a date, and a copy on file before the last crew leaves. That is most of the job, and it is far easier to do on the first day than to fix on the last.