The rule in plain words
Under Virginia's contractual disputes statute, you have to send your claim in writing no later than 60 days after final payment. That is a hard deadline tied to one specific event: the final payment on the contract.
The statute puts it directly: contractual claims, for money or other relief, must be submitted in writing no later than 60 days after final payment.
Sixty days sounds generous. In practice, it is not. Final payment often lands while your crews are still chasing closeout paperwork. Change orders, retainage releases, and lien waivers compete for attention. Two months can vanish while you wait for a response from the general contractor's office.
Why "written" matters
The statute says the claim must be submitted in writing. A phone call to the contract administrator does not satisfy that requirement. A hallway conversation at the job trailer does not either.
What counts as written? The statute's plain language says a written submission. Keep it simple: a dated letter or email that clearly states the claim, the amount or relief sought, and the contract reference. Save the delivery proof. Save the read confirmation if you have it.
Start the clock correctly with early notice
There is an earlier step most owners miss. You must give written notice of your intention to file a claim at the time of the occurrence or the beginning of the work on which the claim is based.
In plain terms: the moment the problem shows up — the extra work you were ordered to do, the condition that changed the scope — you put a written notice on file. Not a month later. Not when the final invoice bounces. At the time.
This early notice does not replace the 60-day filing. It complements it. You send notice when the trouble starts, and you file the full claim within 60 days of final payment. The first shows contemporaneous intent. The second meets the statutory deadline.
A practical rhythm: build a short notice form. When a crew lead reports a change, your office sends a dated notice that day. Log it. Then, when final payment arrives, the 60-day clock starts with a clean paper trail already behind you.
What happens while you wait
Claim pendency does not freeze your money. The statute is clear: pendency of claims shall not delay payment of amounts agreed due in the final payment.
Read that carefully. If the public body agrees a sum is due at final payment, that sum gets paid even while your claim sits open. You do not have to choose between dropping the claim and collecting the undisputed balance.
For a small firm, that distinction matters. It protects cash flow while you work the dispute.