The disclosure statement under RCW 18.27.114 is a written paper you hand a consumer. It states that your contractor registration with the state of Washington is active, gives your registration number, and states the bond or deposit you posted with the state. It also carries two warnings in the statute's own words: that the bond or deposit might not be enough to cover a claim from the work under that contract, and that the same bond is not reserved for that one customer because it covers all of your work.
That statement matters to your wallet in a second, less obvious way. RCW 18.27.114(4) says you cannot bring or maintain a lien claim under chapter 60.04 RCW on a contract covered by the section unless you allege and prove you gave the customer a copy of the disclosure statement as subsection (1) requires. Skip the paper and your lien claim runs into a statutory wall you have to prove your way past.
The section also makes skipping it a ticket. Failure to comply constitutes an infraction under that chapter.
You also owe a second notice later. If your registration expires, or the department revokes or suspends it, you must tell the consumer while the contract is still open, before completion or another end of the job. RCW 18.27.114(3) sets that duty.
Two contracts sit outside the section. Subsection (5) names them, and that carve-out is the point of this post.